June Paving Project


Event Date:

Event Time:
7:00 am - 4:00 pm

Beginning the morning of Monday, June 2, Bennett Paving will continue Belfair's multi-year Pavement Preservation Program. Over a five-day work schedule spanning 11 calendar days, fog seals will be applied to select roadways to create a durable wearing surface over the existing asphalt. Work hours will be 7:00 AM to 4:00 PM, weather permitting.

The following roadways will be affected during this period:

  • Summerton Drive
  • Cooper Court
  • Chattoga Court
  • Newberry Court

Important Information:

  • Day One (Monday, June 2): Crack sealing will take place across all scheduled areas. This process should dry relatively quickly and cause minimal disruption.
  • Day Two (Tuesday, June 3): Fog Seal application begins. Cooper Court and Chattoga Court will be completely closed during this time. Please plan accordingly.

Important Information:

  • The day before scheduled work, please turn off your home's irrigation system.
  • Be aware of traffic cones and barriers indicating road closures or changes in traffic direction. These measures are in place for your safety and the safety of the workers.
  • No curbside parking on affected roads on the day of work. Please use the Clubhouse Parking Lot as an alternative if needed.
  • Please notify contractors, landscapers, and vendors of the schedule.
  • No work will be completed on weekends.
  • To avoid damage to your vehicle or driveway, please do not drive on the application until after 8:00 PM.
  • Monitor the Belfair Website and App for updates.

We will continue to send updates on Bennett's progress, any schedule changes, and parking instructions.